  "id": "riskg-management-of-change",
  "type": "risk-guideline",
  "languages": {
    "en": {
      "id": "riskg-management-of-change",
      "lang": "en",
      "type": "risk-guideline",
      "title": "Management of Change (MOC)",
      "shortDefinition": "Management of change (MOC) is a formal procedure that reviews and authorises structural, technical, process and organisational changes before implementation to identify new fire, explosion and property damage risks.",
      "synonyms": [
        "MOC",
        "Change management"
      ],
      "linesOfBusiness": [
        "Property",
        "Engineering"
      ],
      "jurisdictions": [
        "Global"
      ],
      "tags": [
        "Risk Management",
        "Loss prevention"
      ],
      "relations": {
        "relatedTerms": [
          "riskg-contractor-management",
          "riskg-risk-improvement-recommendations",
          "riskg-shutdown-startup-risks"
        ],
        "partOf": [
          "riskg-fire-safety-management"
        ],
        "appliesTo": [
          "cov-property-all-risks",
          "cov-business-interruption"
        ],
        "regulatedBy": [],
        "relevantFor": [],
        "insurableVia": [],
        "mitigatedBy": [],
        "comprises": [],
        "alternativeTo": [],
        "complementedBy": []
      },
      "attribute": null,
      "profile": null,
      "coverageProfile": null,
      "clause": null,
      "legalBasis": [],
      "standards": [],
      "reviewStatus": "expert-reviewed",
      "reviewedBy": "Guido Hesse, Hesse Group Holding AG",
      "lastReviewed": "2026-09-04",
      "version": "0.1.0",
      "updated": "2026-09-01",
      "generated": {
        "by": "cursor-agent/claude-sonnet-5",
        "at": "2026-09-01T00:00:00.000Z"
      },
      "verified": [
        {
          "by": "human:ghesse",
          "at": "2026-09-04T00:00:00.000Z",
          "method": null
        }
      ],
      "staleAfter": null,
      "url": "https://hgh.ch/lexikon/en/knowledge/risk-engineering/management-of-change/",
      "alternateUrl": "https://hgh.ch/lexikon/de/wissen/risk-engineering/aenderungsmanagement/",
      "body": "## Why changes create risk\n\nNew construction, alterations, process changes, new machinery or altered materials frequently change existing hazard profiles unnoticed: fire compartments are breached, suppression systems no longer cover new stored commodities, or temporary arrangements from a construction phase are never reinstated. Without formal review, such deviations often remain undetected until a loss occurs.\n\n## The MOC process\n\nA change request describes the nature, scope and reason for the proposed change and is reviewed and formally authorised by the relevant functions – operations, maintenance, fire safety, occupational safety – before implementation. Any deviation from the original condition (i.e. not a straight replacement in kind) triggers a fresh hazard review; once work is complete, the change is documented and reflected in drawings, operating procedures and training materials. Start-up and shut-down phases of process plant are particularly critical, since a large share of process-related losses occur during these transitions.\n\n## Relevance for insurance\n\nUnderwriters treat an established management of change programme as evidence that risk deterioration is identified systematically rather than discovered by chance at the next risk survey. The absence of management of change is a frequent reason why approved protection concepts no longer match the as-built, insured risk."
    },
    "de": {
      "id": "riskg-management-of-change",
      "lang": "de",
      "type": "risk-guideline",
      "title": "Änderungsmanagement (Management of Change)",
      "shortDefinition": "Änderungsmanagement (Management of Change) ist ein formales Verfahren, das bauliche, technische, prozessuale und organisatorische Änderungen vor ihrer Umsetzung auf neue Brand-, Explosions- und Sachschadenrisiken prüft und freigibt.",
      "synonyms": [
        "Management of Change",
        "MOC"
      ],
      "linesOfBusiness": [
        "Sach",
        "Technische Versicherung"
      ],
      "jurisdictions": [
        "Global"
      ],
      "tags": [
        "Risikomanagement",
        "Schadenverhütung"
      ],
      "relations": {
        "relatedTerms": [
          "riskg-contractor-management",
          "riskg-risk-improvement-recommendations",
          "riskg-shutdown-startup-risks"
        ],
        "partOf": [
          "riskg-fire-safety-management"
        ],
        "appliesTo": [
          "cov-property-all-risks",
          "cov-business-interruption"
        ],
        "regulatedBy": [],
        "relevantFor": [],
        "insurableVia": [],
        "mitigatedBy": [],
        "comprises": [],
        "alternativeTo": [],
        "complementedBy": []
      },
      "attribute": null,
      "profile": null,
      "coverageProfile": null,
      "clause": null,
      "legalBasis": [],
      "standards": [],
      "reviewStatus": "expert-reviewed",
      "reviewedBy": "Guido Hesse, Hesse Group Holding AG",
      "lastReviewed": "2026-09-04",
      "version": "0.1.0",
      "updated": "2026-09-01",
      "generated": {
        "by": "cursor-agent/claude-sonnet-5",
        "at": "2026-09-01T00:00:00.000Z"
      },
      "verified": [
        {
          "by": "human:ghesse",
          "at": "2026-09-04T00:00:00.000Z",
          "method": null
        }
      ],
      "staleAfter": null,
      "url": "https://hgh.ch/lexikon/de/wissen/risk-engineering/aenderungsmanagement/",
      "alternateUrl": "https://hgh.ch/lexikon/en/knowledge/risk-engineering/management-of-change/",
      "body": "## Warum Änderungen Risiken schaffen\n\nNeubauten, Umbauten, Prozessänderungen, neue Maschinen oder geänderte Materialien verändern bestehende Gefährdungsbilder häufig unbemerkt: Brandabschnitte werden durchbrochen, Löschanlagen decken neue Lagergüter nicht mehr ab, oder provisorische Lösungen aus der Bauphase werden nie wieder rückgebaut. Ohne formale Prüfung bleiben solche Abweichungen oft bis zum Schadenfall unentdeckt.\n\n## Ablauf eines MOC-Verfahrens\n\nEin Änderungsantrag beschreibt Art, Umfang und Grund der geplanten Änderung und wird von den betroffenen Fachstellen – Betrieb, Instandhaltung, Brandschutz, Arbeitssicherheit – vor der Umsetzung geprüft und formell freigegeben. Abweichungen vom ursprünglichen Zustand (kein «Replacement in kind») lösen eine erneute Gefährdungsbeurteilung aus; nach Abschluss der Arbeiten wird die Änderung dokumentiert und in Pläne, Betriebsanweisungen und Schulungsunterlagen nachgeführt. Besonders kritisch sind Anfahr- und Abfahrphasen von Prozessanlagen, da hier ein Grossteil der prozessbezogenen Schadenfälle entsteht.\n\n## Versicherungsrelevanz\n\nUnderwriter werten ein etabliertes Änderungsmanagement als Beleg dafür, dass Risikoverschlechterungen systematisch erkannt und nicht erst bei der nächsten Risikobesichtigung zufällig entdeckt werden. Fehlendes Änderungsmanagement ist eine häufige Ursache dafür, dass genehmigte Schutzkonzepte im Ist-Zustand nicht mehr der versicherten Risikolage entsprechen."
    }
  }
}